Date: August 2021
Industry: Infrastructure – Commercial Buildings / HVAC
Application: Chilled Water Pump & Pipe Systems
Region: UAE
Enquiry NowA high-rise commercial tower in Dubai faced noise and vibration complaints from tenants due to mechanical vibrations traveling from the HVAC plantroom to upper floors. The existing rigid pipework offered no flexibility, and the building management required a retrofit solution without structural modifications or system shutdown.
FlexiBel supplied single-arch rubber bellows with control rods and EPDM construction, rated for chilled water service. The bellows were installed between pump discharge and main headers to isolate mechanical vibration and absorb minor piping misalignment. The solution allowed bolt-on replacement during low-load hours without full system shutdown.
Post-installation monitoring showed a noticeable reduction in transmitted vibration and audible noise. The solution resolved tenant complaints and improved system stability. FlexiBel was later contracted to supply similar joints for the building's second tower under construction.